The project site has an optimal orientation, allowing for maximum energy production throughout the year.

The mounting structure used is from the Ataro Clima series, providing high durability and reliability. We installed Jinko Solar N-type photovoltaic modules with a unit capacity of 590 Wp. Energy conversion is managed by Huawei SUN2000 string inverters, ensuring the system’s efficiency and stability.

The total capacity of the project is 2000 kWp, with the entire implementation— from planning to the final construction details—completed by GES Energy under the FULL EPC model.

The next phase of the project includes an energy storage system with batteries, which will enhance the flexibility and energy independence of the installation.