Project Development
The development of photovoltaic projects is a complex and time-consuming task that requires excellent knowledge of legislation and the market. The development of any project inevitably involves risk, a long period of time and a huge financial resource. “Greentech Engineering Solutions” JSC has 14 years of experience in the development of projects in the field of renewable energy sources and is a proven reliable partner in Bulgaria and abroad.
Suitable terrain
Choosing a suitable site for your PV project is a difficult task that requires a thorough knowledge of local regulations and grid capabilities.
Preliminary design
The preliminary design is the first step after identifying the suitable terrain. It will set the primary technical parameters of the potential project.
Grid connection permit
The preliminary design will serve you to get a grid connection permit of your photovoltaic power plant from the TSO or the DSO grid operator.
Technical design
After receiving the grid connection permit, GES will prepare for you a comprehensive technical design in order to obtain a building permit
Construction
After obtaining a building permit from the local municipality, we will take care of the construction of the photovoltaic plant in the shortest possible time.
Commissioning
After successfully passing 72 hour tests, we will ensure that your power plant is up and running in the shortest possible time.
Suitable terrain
Choosing a suitable site for your PV project is a difficult task that requires a thorough knowledge of local regulations and grid capabilities.
Preliminary design
The preliminary design is the first step after identifying the suitable terrain. It will set the primary technical parameters of the potential project.
Grid connection permit
The preliminary design will serve you to get a grid connection permit of your photovoltaic power plant from the TSO or the DSO grid operator.
Technical design
After receiving the grid connection permit, GES will prepare for you a comprehensive technical design in order to obtain a building permit
Construction
After obtaining a building permit from the local municipality, we will take care of the construction of the photovoltaic plant in the shortest possible time.
Commissioning
After successfully passing 72 hour tests, we will ensure that your power plant is up and running in the shortest possible time.